Section 3 of the Ring Road extends from Hamilton Highway at Fyansford to the Princes Highway, Waurn Ponds.
The road alignment was announced in July 2006 following consideration by an Independent Panel of an Environment Effects Statement and Planning Scheme Amendment. More than than 230 public submissions were received.
Media Release 07/07/2006 [PDF 16 KB]
An $108.3 million contract for the works was awarded to Abigroup Contractors. Construction commenced in September 2007 with works due for completion in late 2009.
Media Release 25/07/2007 - Award of Contract [PDF 47 KB]
Media Release 14/09/2007 - Sod Turning Event [PDF, 19 KB]
Features and benefits
The Ring Road from Fyansford to Waurn Ponds is being constructed as a four-lane freeway, capable of being upgraded to six lanes in future. It includes 7.5 kilometres of road and bridge works with interchanges at the Hamilton Highway, Barrabool Road and the Princes Highway; overpasses at Wandana Drive and Thornhill Road/Pigdons Road; and 115 metre-long twin bridges spanning the Barwon River.
The Ring Road is expected to carry approximately 25,000 vehicles per day, with motorists avoiding up to 29 sets of traffic lights and enjoying significant travel time savings.
Architecturally designed noise walls, built from weathering steel, will be complemented by significant landscaping. Habitat for local wildlife will be provided by the inclusion of thousands of native and indigenous trees, shrubs and grasses.
Additional Information on the Geelong Ring Road is available via the following links:
Top of page
Construction activities currently underway include:
- Earth works between the Barwon River and Wandana Drive
- Barwon River bridge foundations
- Drainage works and service relocations
Construction of major interchanges and overpasses will have implications for local traffic and will require temporary changes to speed limits, road closures and detours. These will be communicated through advertising in local media or letterbox drops to affected landowners.
VicRoads and Abigroup will work together to ensure traffic impacts during construction are minimised.
Permanent road closures for Section 3 of the Ring Road will include:
Road realignments will include:
- Three Springs Road
- DeGoldis Road
- Thornhill Road and Pigdons Road
Bridges:
- Hamilton Highway
- Barwon River
- Barrabool Road
- Wandana Drive (south)
- Thornhill Road and Pigdons Road
Top of page
Publications, maps & photos
Section 3 map [PDF 39 KB] Section 3 Fact Sheet [PDF 855 KB]
Managing the environment
The Geelong Ring Road EES/PSA
An Environment Effects Statement (EES) and associated Planning Scheme Amendment (PSA) for Section 3 was prepared and released for public exhibition in August 2005.
The EES examined in detail alternative route alignments, south of the Hamilton Highway, Fyansford to the Princes Highway, Waurn Ponds. The proposed alignment options were measured against environmental, social and economic objectives developed in consultation with stakeholders, and through independent consultant investigations.
Benefits and impacts were carefully assessed through studies such as:
- air, noise and water
- flora and fauna
- cultural heritage
- landscape and visual impact
- roads and traffic
- social impact
More information on the EES process is available at the Department of Sustainability and Environment website: www.dse.vic.gov.au
Top of page